Serving as an extension to District staff, KEH provided consultant coordination, design review, and constructability review for the implementation of District CIP projects. The CIP projects include replacement of approximately 3.5 miles of potable water and recycled water pipelines, isolation valve replacement program, replacement of nine pressure reducing stations, and improvements to the District’s Badger Water Treatment. Our team assisted in developing project technical specifications, front end documents, and construction sequencing plans. In addition, KEH also supported the District in developing bid addendums, and contract document clarifications during the bid phase of the projects.