Miramar Water Treatment Plant Clear Well Program Management

City of San Diego, CA

 

KEH is currently providing program / project management assistance and support on the Miramar WTP Clearwell Project. The project involves the construction of two new treated water clearwell with a storage volume of approximately 58 million gallons, a new Chlorine Contact Tank for the ultimate capacity of 240 mgd, a new maintenance building and a 240 mgd pump station. Services included the preparation of project schedules, attending progress meetings with the City, coordination of subconsultants, assistance in preparation of permitting plan, constructability and design reviews of the Basis of Design Report, and design submittals.